Start Phase 5
PRIMA Nufărul
oradea
Construction begins on Phase 5 of the Prima Nufărul residential project.
259 apartments
Completion of Phase 4
PRIMA Nufărul
oradea
Completion of construction for Phase 4 of the Prima Nufărul residential project.
347 apartments
Start Phase 4
PRIMA Nufărul
oradea
Construction begins on Phase 4 of the Prima Nufărul residential project.
347 apartments
Phase 3 Completion
PRIMA Nufărul
oradea
Completion of construction for Phase 3 of the residential project Prima Nufărul.
42 apartments
Phase 2 Completion
PRIMA Nufărul
oradea
Completion of construction for Phase 2 of the residential project Prima Nufărul.
75 apartments
Start Phase 2
PRIMA Nufărul
oradea
Construction begins on Phase 2 of the Prima Nufărul residential project.
75 apartments